In SAP MM as at ECC6.0 EhP6, the Purchasing Processing Time used for time calculation during MRP run for Re-Order point material to determine the delivery date is setup in ______________________.
(only one answer)
A) Material Master Purchasing Data view.
B) Material Master MRP 2 Data view.
C) Purchasing Info Record.
D) MRP Plant Parameter in the MRP customizing.
E) Purchasing Organization in the Enterprise Structure customizing.
.
(only one answer)
A) Material Master Purchasing Data view.
B) Material Master MRP 2 Data view.
C) Purchasing Info Record.
D) MRP Plant Parameter in the MRP customizing.
E) Purchasing Organization in the Enterprise Structure customizing.
.
Answer: D
ReplyDeleteIMG - MM - CBP - Plant Parameter - Carry Out Overall Maintenance of Plant Parameter
ReplyDeleteSelect a Plant
External Procurement ICON