In SAP PP or PPPI planning, which of the following setting is a pre-requisite for Planning Strategy to ignore stocks for MRP Planning ?
(Only one answer)
A) Assign the Gross Planning indicator in the BOM header.
B) Assign the Gross Planning indicator at the MRP Group parameter for the Material.
C) Make sure all Storage Location assigned tonthe Material with ignore storage location stock indicator.
D) Assign the Gross Planning indicator to the MRP3 view in the Material.
E) Set the ignore storage location indicator in the MRP run initial screen.
.
(Only one answer)
A) Assign the Gross Planning indicator in the BOM header.
B) Assign the Gross Planning indicator at the MRP Group parameter for the Material.
C) Make sure all Storage Location assigned tonthe Material with ignore storage location stock indicator.
D) Assign the Gross Planning indicator to the MRP3 view in the Material.
E) Set the ignore storage location indicator in the MRP run initial screen.
.
Answer: D
ReplyDelete2 things:
ReplyDelete. Gross Planning indicator in thr Requirement type for Startegy 11
. Gross Planning indicator in the Material Master MRP 3 view