In SAP PP MRP, the following are settings in the Reduction Strategy to reduce operation times for Routing operations EXCEPT ?
(only one answer)
A) Queue time.
B) Wait time.
C) Move time.
D) Split.
E) Overlap.
.
(only one answer)
A) Queue time.
B) Wait time.
C) Move time.
D) Split.
E) Overlap.
.
Answer: B
ReplyDeleteIMG - Production - CRP - Operations - Scheduling - Reduction Strategies - Define reduction strategies planned/production order