In SAP MM or PP MRP, review the following settings in the Stock Requirements List and determine MRP calculation.
(only one answer)
A) One Planned Order of 50 and a Second Planned Order of 12.
B) One Planned Order of 500.
C) One Planned Order of 50.
D) One Planned Order of 62.
E) One Planned Order of 100.
.
(only one answer)
A) One Planned Order of 50 and a Second Planned Order of 12.
B) One Planned Order of 500.
C) One Planned Order of 50.
D) One Planned Order of 62.
E) One Planned Order of 100.
.
Since the net requirement is 62, and it is above the minimum of 50 but below the maximum of 500, the system would just propose one planned order of 62.