In SAP MM and PP MRP, which of the following scheduling elements is not used when MRP run performs a backward scheduling for an external procurement planned order ?
(only one answer)
A) Goods Receipt processing time.
B) Planned Delivery time.
C) Release Period.
D) Purchasing Processing time.
E) Opening Period.
.
(only one answer)
A) Goods Receipt processing time.
B) Planned Delivery time.
C) Release Period.
D) Purchasing Processing time.
E) Opening Period.
.
Answer: C
ReplyDeleteRelease period is only for internal procurement element scheduling.