In SAP PP, select the correct description of the PP Safety Time.
(only one answers)
A) The order proposals are brought forward by the number of calendar days specified in the safety time, the actual requirements are not changed and the Safety Time is set in the MRP Group parameter.
B) The order proposals are brought forward by the number of working days specified in the safety time, the actual requirements are also brought forward and the Safety Time is set in the MRP 2 view.
C) The order proposals are brought forward by the number of calendars days specified in the safety time, the actual requirements are also brought forward and the Safety Time is set in the MRP Group parameter.
D) The order proposals are brought forward by the number of working days specified in the safety time, the actual requirements are are not changed and the Safety Time is set in the MRP 2 view.
E) The order proposals are brought forward by the number of working days specified in the safety time, the actual requirements are are not changed and the Safety Time is set in the MRP Group parameter.
.
(only one answers)
A) The order proposals are brought forward by the number of calendar days specified in the safety time, the actual requirements are not changed and the Safety Time is set in the MRP Group parameter.
B) The order proposals are brought forward by the number of working days specified in the safety time, the actual requirements are also brought forward and the Safety Time is set in the MRP 2 view.
C) The order proposals are brought forward by the number of calendars days specified in the safety time, the actual requirements are also brought forward and the Safety Time is set in the MRP Group parameter.
D) The order proposals are brought forward by the number of working days specified in the safety time, the actual requirements are are not changed and the Safety Time is set in the MRP 2 view.
E) The order proposals are brought forward by the number of working days specified in the safety time, the actual requirements are are not changed and the Safety Time is set in the MRP Group parameter.
.
Answer: D
ReplyDeleteThe safety time is an additional float after production, the purpose is mainly to avoid possible shortages due to less then desired delivery reliability from the supplier. The order proposal will be brought forward by number of working days from the desired requirement date but it cannot change the demand requirement date.