In SAP Material Master standard MRP data view, which of the following is not a mandatory data fields to be entered when MRP type with an MRP Procesure has been enetered in the MRP 1 data view ?
(onky one answer)
A) MRP Group.
B) MRP Controller.
C) Lot Size Key.
D) Procurement Type,
E) Scheduling Margin Key.
.
(onky one answer)
A) MRP Group.
B) MRP Controller.
C) Lot Size Key.
D) Procurement Type,
E) Scheduling Margin Key.
.
Answer: A
ReplyDeleteMRP Group is always optional regardless of MRP Type if no other field selectin has been defined manually.