This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, July 23, 2014

Question no 2491 : MRP view

In SAP Material Master standard MRP data view, which of the following is not a mandatory data fields to be entered when MRP type with an MRP Procesure has been enetered in the MRP 1 data view ?

(onky one answer)

A)    MRP Group.
B)    MRP Controller.
C)    Lot Size Key.
D)    Procurement Type,
E)    Scheduling Margin Key.
.

2 comments:

  1. MRP Group is always optional regardless of MRP Type if no other field selectin has been defined manually.

    ReplyDelete