In SAP PP or PPPI, if you would like to backflush all materials assigned to an operation when the operation is confirmed, which of the following optimal setting would you recommend ?
(more than one answers)
A) Set 'Always Backflush' for thr Backflush indicator at the MRP2 view in the Material Master.
B) Set 'Depending on Work Center' for the Backflush indicator at the MRP2 view in the Material Master.
C) Create a Phantom material for all the components and assigned the Backflush indicator to thr Phantom material.
D) Set the Backflush indicator to the Work Center Master.
E) Set the Backflush indicator for the operation at the Confirmation screen.
.
(more than one answers)
A) Set 'Always Backflush' for thr Backflush indicator at the MRP2 view in the Material Master.
B) Set 'Depending on Work Center' for the Backflush indicator at the MRP2 view in the Material Master.
C) Create a Phantom material for all the components and assigned the Backflush indicator to thr Phantom material.
D) Set the Backflush indicator to the Work Center Master.
E) Set the Backflush indicator for the operation at the Confirmation screen.
.
Answer: B, D
ReplyDeleteSince all material assigned to an operation is to be backflushed:
ReplyDelete1) Material Master MRP2 view 'Depending on Work Center' backflush indicator.
2) Set the Bakflsuhung indicator at the awork Center.