In SAP PP, what are the possible methods of setting an assembly material to 'Phantom' behavior ?

(more than one answers)

A)    Special procurement key in the MRP 2 data view in the material master.
B)    Item category of the material assigned to the BOM.
C)    Explosion type in the BOM item detail.
D)    Special procurement key in the BOM item detail.
E)    Special procurment key in the BOM header.
.

3 comments:

  1. C) This is tricky because there is an Explosion type indicator to switch off the Phantom Special Procurement in the MRP 2 view.

    ReplyDelete
  2. A, D, E) The special procurement key '50' (Phantom) can be set either in the MRP 2 data view or the item detail and not at the BOM Header.