This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, July 25, 2014

Question no 2499 : Long Term Planning Simulated S/R List

In SAP PP ECC6.0 EhP5, which of the following can you perform in the Simulated Stock Requirement List in the LTP module in SAP PP ?

(more than one answers) 

A)    Convert Simulated Firmed Planned Orders to Purchase Orders.
B)    Change the Simulated Planned Orders quantities.
C)    Activate the non-active Planned Independent Requirements.
D)    Set the firming indicator to the Simulated Planned Orders.
E)    Check the capacity situation of the material.
.

5 comments:

  1. A, D) You can set the firming indicator to the Simulated Planned Orders but you cannot convert any Planned Orders in the Simulated S/R List in LTP in Execution MRP Elements. It is possible to copy the firmed Simulated Planned Orders to the Operative S/R List but this can only be done in the Operative Environment's interactive planning run.

    ReplyDelete
  2. A, B) You cannot convert Simulated Planned Orders to Execution MRP elements in the Simulated S/R List, However you can change the quantities within it.

    ReplyDelete
  3. C) Activation of the PIR can be done in the LTP Scenario and not within the Simulated S/R List.

    ReplyDelete
  4. E) If you run the LTP with Lead Time Scheduling, the capacity is calculated and from within the Simulated S/R List, you can review the Simulated Capacity Situation.

    ReplyDelete