In SAP PP ECC6.0 EhP5, which of the following can you perform in the Simulated Stock Requirement List in the LTP module in SAP PP ?
(more than one answers)
A) Convert Simulated Firmed Planned Orders to Purchase Orders.
B) Change the Simulated Planned Orders quantities.
C) Activate the non-active Planned Independent Requirements.
D) Set the firming indicator to the Simulated Planned Orders.
E) Check the capacity situation of the material.
.
(more than one answers)
A) Convert Simulated Firmed Planned Orders to Purchase Orders.
B) Change the Simulated Planned Orders quantities.
C) Activate the non-active Planned Independent Requirements.
D) Set the firming indicator to the Simulated Planned Orders.
E) Check the capacity situation of the material.
.
Answer: B, D, E
ReplyDeleteA, D) You can set the firming indicator to the Simulated Planned Orders but you cannot convert any Planned Orders in the Simulated S/R List in LTP in Execution MRP Elements. It is possible to copy the firmed Simulated Planned Orders to the Operative S/R List but this can only be done in the Operative Environment's interactive planning run.
ReplyDeleteA, B) You cannot convert Simulated Planned Orders to Execution MRP elements in the Simulated S/R List, However you can change the quantities within it.
ReplyDeleteC) Activation of the PIR can be done in the LTP Scenario and not within the Simulated S/R List.
ReplyDeleteE) If you run the LTP with Lead Time Scheduling, the capacity is calculated and from within the Simulated S/R List, you can review the Simulated Capacity Situation.