This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, June 28, 2019

Question no 3649 : Storage Location in Goods Receipt

In SAP MM as at ECC6.0 EHP7, which of the following scenarios do not require a Storage Location entry at Goods Receipt ?

(more than one answers)

A)  Goods Receipt for Gr-Based Invoice.
B)  Goods Receipt into Valuated GR-Blocked Stock.
C)  Goods Receipt into Non-Valuated GR-Blocked Stock.
D)  Goods Receipt for Consumables Purchase Order.
E)  Goods Receipt for Blanket Purchase Order.
.

Answers: B, C, D

A) GR-Based IV setting do not necessary result in non SLoc requirement.
B,C) GR-Blocked Stock is at the Plant level.
D) Consumables do not require a SLoc.
E) Blanket PO has no GR function.

Wednesday, June 26, 2019

Question no 3648 : Equipment Master

In SAP PM as at ECC6.0 EhP6, which of the following are correct assignments possible for an Equipment Master ?

(more than one answers)

A)  Exactly one permit can be assigned to an Equipment Master.
B)  Exactly one Construction Type can be assigned to an Equipment Master.
C)  One or more sub-Equipments can be assigned to a Superior Equipment.
D)  An Equipment Master can be assigned to one or more Functional Location.
E)  One or more Cost Centers can be set as default to an Equipment Master.
.

Answers: B, C


Wednesday, June 19, 2019

Question no 3647 : Valuation Variant

In SAP PM as at ECC6.0 EhP6, which of the following Cost features are provided by the Valuation Variant assigned to the Costing Variant ?

(more than one answers)

A)  Determine the Material Cost.
B)  Determine the Labor Cost.
C)  Determine the Overhead Cost.
D)  Determine the Valuation Type.
E)  All of the above.
.

Answers: A, B, C


Wednesday, June 12, 2019

Question no 3646 : Purchase Requisition

In SAP MM as at ECC6.0 EhP6, which of the following are correct about Purchase Requisitions ?

(more than one answers)

A)  A PR can be saved with or without a Plant.
B)  A PR can be saved with or without a Purchasing Group.
C)  A PR can be saved with or without a Purchasing Organization.
D)  A PR can be saved with or without a Storage Location.
E)  A PR can be saved with or without a Delivery Date.
.

Answer: B, C, D

In Standard SAP Delivery, Plant and Delivery Date is Mandatory by design.

Sunday, June 9, 2019

Question no 3645 : Quotation Comparison

In SAP MM as at ECC6.0 EhP6, which of the following functions can be executed via ME47 Quotation Comparison ?

(more than one answers)

A)  Reject a Quotation.
B)  Generate a Purchasing Info Record.
C)  Generate a Purchase Requisition.
D)  Change Quotation Prices.
E)  Generate a Source List.
.

Answer: A, B, D

So far as the version mentioned:
A) From within ME47, you can navigate to a Quotation to check a Rejection Indicator where a Rejection Letter can be a Message Output to be send to the vendor.
B) An indicator can be checked to Generate the PIR with or without Plant (depending on if the RFQ was initially created with or without a Plant) and relevant IMG.
D) ME47 allows you to navigate to the change mode of the Quotation to set the Pricing Conditions.
.

Wednesday, June 5, 2019

Question no 3644 : MRP Elements

In SAP MM/PP as at ECC6.0 EhP6, which of the following is not displayed as an MRP Element in the Stocks Requirements List ?

(more than one answer)

A)  RFQ.
B)  Purchase Requisition.
C)  Reservations.
D)  Contract.
E)  Planned Orders.
.

Answers: B, C, E

Not RFQ nor Contract.