In SAP MM/PP MRP as at ECC6.0 EhP6, which of the following MRP elements cannot be considered by the tolerances for re-scheduling messages at the Plant Parameter OPPQ ?
(only one answer)
A) Firmed Planned Orders.
B) Planned Orders.
C) Production Orders.
D) Fixed Purchase Requisitions.
E) Purchase Orders.
.
(only one answer)
A) Firmed Planned Orders.
B) Planned Orders.
C) Production Orders.
D) Fixed Purchase Requisitions.
E) Purchase Orders.
.
Answer: B
ReplyDeletePlanned Orders effectively will be managed by the next MRP run (whether removing it or changing dates to match the demand); therefore, they need not have re-scheduling message to the planner. However, all the other firmed orders such as PR, PO, Prod Order, firmed PR, firmed Planned Orders, and/or Delivery Schedules cannot be changed by the next MRP run; therefore if there is a change of demand/supply imbalance, the purpose of the re-scheduling message is exactly for making this note to the planners.