In SAP MM and PP MRP, which of the following MRP Area definition os valid ?

(More than one answers)

A)   Only one Storage Location can be assigned to an MRP Area.
B)   Only one Sub-Contractor can be assigned to an MRP Area.
C)   One or more Storage Locations can be assigned to an MRP Area.
D)   One or more Sub-Contractor can be aasignes to an MRP Area.
E)   Only one default goods receipt Storage Location can be assigned to an MRP Area.
.

2 comments:

  1. MRP Area Type '2' is for Storage Location MRP:
    . One or more Storage Locations can be assigned to it.
    . One default goods receipt storage location can be assigned to it.

    MRP Area Type '3' is for Sub-Contractor MRP.
    . Exactly one sub-contractor can be assigned to an MRP Area.

    ReplyDelete