In SAP MM and PP MRP, the Header screen sequence in the Stock Requirement List is detemined by which ofnthe following ?
(only one answer)
A) Material Type.
B) MRP Group.
C) MRP Controller.
D) User Parameter ID.
E) MRP Type.
.
(only one answer)
A) Material Type.
B) MRP Group.
C) MRP Controller.
D) User Parameter ID.
E) MRP Type.
.
Answer: E
ReplyDeleteCreate Screen Sequence here:
ReplyDeleteIMG - Production - MRP - Evaluations - Define Screen Sequence for Header Data
Assign Screen Sequence to MRP type here:
IMG - Production - MRP - Master Data - Check MRP Types