This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Showing posts with label PLM310 Unit 06 Multiple Counter Plan. Show all posts
Showing posts with label PLM310 Unit 06 Multiple Counter Plan. Show all posts

Tuesday, June 28, 2016

Question no 3195 : Preventive Maintenance Scenario

In SAP PM as at ECC6.0 EhP6, consider the following requirement

"A customer wants a Preventive Maintenance Plan for executing the company vehicles for plan due either every 3 months or 5000 km", the job is to be executed by an external vendor".

which of the following type of Maintenance Plan is most appropriate.

(only one answer)

A)   Single-Cyle Plan
B)   Strategy Plan.
C)   Multi-Counter Plan.
D)   External Procurement Maintenance Plan.
E)   Multi-Characteristics Plan.

Sunday, June 12, 2016

Question no 3169 : Hierarchy in SAP Maintenance Planning

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following Maintenance Plan scenario do not allow the use of Hierarchy ?

(more than one answers)

A)   Single Cycle Plan.
B)   Time-Based Strategy Plan.
C)   Performance-Based Strategy Plan.
D)   Mutli-Counter Plan.
E)   External Services Plan.

Friday, January 16, 2015

Question no 2576 : Multi-Counter Plan

In SAP EAM for Plant Maintenance as at ECC6.0 EhP7, which of the following statements do not correctly depict the features of Multi-Counter Plan ?

(more than one answer)

A)   When the Task List is assigned to the Maintenance Plan, the system will check if the Cycle Set assigned to the Task List header is the same as the Cycle Set assigned to the Multi-Counter Plan initial screen.
B)   You should have a minimum of 2 Maintenance Items when creating a Multi-Counter Plan with a Cycle Set Sequence.
C)   You can shift the Cycle Set Call to which sequence call while perform initial scheduling of the Multi-Counter Plan in IP10, this will allow scheduling to select the Task List associated with the Cycle Set Sequence from the Maintenance Items.
D)   Call Horizon in the Multi-Counter Plan will allow you to Call the maintenance due earlier.
E)   Cycle Modification factor is allowed for Multi-Counter Plan.
.

Friday, December 3, 2010

Question no : 804 PM Preventive Multiple Counter Plan Scheduling

PLM310 Preventive Maintenance
Unit 06 Maintenance Planning with Cycles of Different Dimensions

In scheduling for Multiple counter plans, the following are not possible:
(more than one answers)

(A) Start.
(B) Restart.
(C) Manual call.
(D) Start in current cycle.
(E) Schedule.
.

Question no : 802 PM Preventive Multiple Counter Plan Characteristics

PLM310 Preventive Maintenance
Unit 06 Maintenance Planning with Cycles of Different Dimensions

Which of the following is true about Multiple counter Plans ?
(more than one answers)

(A) A maximum of one time-based cycle can be used in a multiple counter plan.
(B) Once the cycle set has been included in the maintenance plan, the individual cycles can be changed or deleted.
(C) After the maintenance plan has been created, there is no longer a link between the cycle set and the maintenance plan.
(D) The task list included in the multiple counter plan cannot have reference to a strategy similar to what a time-base strategy method.
(E) You can assign cycles freely to the multiple counter plan. A strategy cannot be used here.
.

Question no : 803 PM Preventive Multiple Counter Master Data

PLM310 Preventive Maintenance
Unit 06 Maintenance Planning with Cycles of Different Dimensions

The different dimensions used for a multiple counter plan is set up in the:
(only one answer)

(A) Strategy.
(B) Characteristics.
(C) Class.
(D) Task list.
(E) Cycle sets.
.

Question no : 801 PM Preventive Multiple Counter Plan Characteristics

PLM310 Preventive Maintenance
Unit 06 Maintenance Planning with Cycles of Different Dimensions

Which of the following is true about Multiple counter Plans ?
(more than one answers)

(A) Start in cycle selection is not available during on-line scheduling for this type of Strategy.
(B) Cycle set can have cycles of different dimensions (for example: time, liters, and throughput).
(C) When the cycle set is assigned to the multiple counter plan, changes to the cycle set in the multiple counter plan has no effect to the cycle set master data.
(D) When the cycle set is assigned to the multiple counter plan, changes to the cycle set in the multiple counter plan updates the cycle set master data.
(E) Multiple counter plans are assigned to the task list header.
.