Question no 3570 : Maintenance Plan for Calibration

In SAP PM as at ECC6.0 EhP7, which of the following determines if an Inspection Lot is generated for Calibration Preventive Maintenance scenario ?

(only one answer)

A)  Order Type is assign with Inspection Type.
B)  Maintenance Category with Call Object Inspection Lot.
C)  QM characteristics are assigned to the Maintenance Item.
D)  Material Master is assigned with Inspection Type.
E)  Maintenance Plan header is set for QM processing indicator.
.

Answer: A

. Order Type must be assigned with Inspection Type
. Task List header assigned with Inspection Point.
. QM characteristics to be assigned to the Calibration Task List operation.

Sunday, April 22, 2018

Question no 3539 : Inspection Type for Maintenance Order Types

In SAP PM as at ECC6.0 EhP6, an Inspection Type can be assigned to the Planning Plant + Order Type combination, what is the purpose ?

(only one answer)

A)  Preventive Maintenance Calibration Plan.
B)  Preventive Maintenance Refurbishment Plan.
C)  Preventive Maintenance Inspection Plan.
D)  Preventive Maintenance QC Plan.
E)  Preventive Maintenance Operational Plan.
.

Answer: A

IMG - PM/CS - Maint.Serv.Processing - Maint.Serv.Orders - Functions and Settings for Order Types - Assign Inspection Types to Maint.Serv. Order Types.
IP41 use Maintenance Plan Category - QM Calibration Plan
Standard SAP use Order Type PM05 (which is assign to Inspection Type 14), IP10 or IP30 will call MO linked to Inspection Lot

Wednesday, August 15, 2012

Question no 1642: Calibration

In SAP PM as of ECC6.0, for Calibration Maintenance Planning, in order to automatically record measuring documents into measuring points from results recording of inspection lot, what setup is necessary ?

(only one answer)

A)    set the automatic on recording parameter indicator in the measuring point category.
B)    set the automatic on recording parameter indicator in the maintenance plan category.
C)    link the inspection characteristics to the measuring point.
D)    assign the the class characteristics used to create the measuring point to the inspection characteristics used in the calibration plan.
E)    assign an appropriate confirmation profile to the user.
.

Friday, December 3, 2010

Question no : 817 PM Preventive Calibration Measurement Reading

PLM310 Preventive Maintenance
Unit 09 Maintenance Plan-Based Test Equipment

If the measurement readings in the inspection lot of a Calibration order lie outside the tolerance where adjustment is necessary:
(more than one answers)

(A) The status of the equipment is set to “Not Available for Use”.
(B) The equipment is flagged for temporary deletion.
(C) The equipment is placed in blocked stocks.
(D) A malfunction report (notification) is generated with the appropriate error codes.
(E) An activity report (maintenance order) is generated with the appropriate error codes.
.

Question no : 816 PM Preventive Task list

PLM310 Preventive Maintenance
Unit 09 Maintenance Plan-Based Test Equipment

For calibration results to be recorded, you would have to :
(only one answer)

(A) assign inspection task list to the maintenance plan.
(B) create inspection task list.
(C) assign master inspection characteristics to the operations in the maintenance task list.
(D) create task list with operation control key “PM10” for inspection operations.
(E) assign inspection task list to the maintenance task list header.
.

Question no : 815 PM Preventive Calibration Inspection Processing

PLM310 Preventive Maintenance
Unit 09 Maintenance Plan-Based Test Equipment

Completing the calibration inspection lot requires the following processing:
(only one answer)

(A) Results recording and Usage Decision.
(B) Results recording and Final Confirmation.
(C) Goods issues and Final Confirmation.
(D) CATS entry and Transfer to Complete.
(E) Service entry and Usage Decision.
.

Question no : 814 PM Preventive Calibration Single-Cycle Plan

PLM310 Preventive Maintenance
Unit 09 Maintenance Plan-Based Test Equipment

When you schedule a calibration related single-cycle maintenance plan, the following will be generated in a successful call:
(more than one answers)

(A) Notification order.
(B) Maintenance order.
(C) Service entry sheet.
(D) Inspection lot.
(E) Purchase requisition.
.

Question no : 813 PM Preventive Calibration Maintenance Plan

PLM310 Preventive Maintenance
Unit 09 Maintenance Plan-Based Test Equipment

In the standard R/3 Plant maintenance system, you use which order type to represent a calibration order in the maintenance plan ?
(only one answer)

(A) PM01
(B) PM02
(C) PM05
(D) PM06
(E) PM07
.