Question no 2522 : Reduction Strategy in MRP run

In SAP MRP, Reduction Strategy is possibly used in which of the following ?

(more than one answers)

A)    When the Start date of an External Procurement Planned Order in the past.
B)    When the Start date of an Internal Procurement Planned Order in the past.
C)     Only when MRP run is executed with 'Lead Time Scheduling' instead of 'Basic Dates'.
D)     A reduction strategy has been set to the Routing Operation.
E)     A reduction startegy has been set to the Routing Header.
.

1 comment:

  1. Reduction Startegy is to reduce operation times such as queue time or transport time, therefore it is only when Routing is selected for MRP run using 'Lead time scheduling' but this can occur if the Start Date is in the Past.