This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Showing posts with label Test : Life Cycle Data Mgmt - Engr Change. Show all posts
Showing posts with label Test : Life Cycle Data Mgmt - Engr Change. Show all posts

Friday, December 26, 2025

Question 4090 : Leading Change Master

In SAP Engineering Change Management as at S/4 1909, which of the following are not possible for a Leading Change Master ?

(more than one answers)

A) Shift Valid From date.
B) Select Object Types.
C) Enter Objects for ECM.
D) Enter Alternative Dates.
E) Allow Release Key.
.

Answer: A, E

Object Types, Objects entry and Alternative Dates, Release key will be allowed in the Change Package.
Valid From dater , and Shift Date, and Release key will be allowed in the Leading Change Master.













Sunday, November 30, 2025

Question 4082 : Alternative dates in Change Number in ECM system

In SAP Engineering Change Management as at S/4 1909, which of the following are the features of "Alternative Dates" in a Change Number ?

(more than one answers)

A) one or more Alternative Dates can be applied to a Change Number.
B) All Alternative Dates must be applied to all the Objects in a Change Number.
C) Alternative Dates feature and Shift Dates feature is the same.
D) Different Objects in a Change Number can be applied to different Alternative Dates.
E) All Objects in the Change Number must be applied to Alternative Dates.
.

Answer: A, D

A) An existing Change Number can be assigned with multiple Alternative Dates.
B, D, E) One can flexibly assign any or selected objects in the Change Number to different Alternative dates entered in the Change Number.
C) Shift Date permanently shifts the original date of the Change Number while Alternative Dates are add-on dates to the original date of the Change Number.


Sunday, May 1, 2016

Question no 3140 : Engineering Change Application for PPDI and PPPI

In SAP PPDI and PPPI as at ECC6.0 EhP6, Engineering Change Notice can be applied to the following objects EXCEPT ?

(only one answer)

A)   Material Master.
B)   Work Center or Resources.
C)   Bills of Material.
D)   Routing.
E)   Recipe.

Wednesday, February 4, 2015

Question no 2588 : Order Change Management

As at ECC6.0 EhP6, to set up Order Change Management (OCM), you would have to assign an ________________________ .
(only one answer)

A)  Overall Profile to the Work Scheduling view in the Material Master.
B)  Overall Profile to the MRP3 view in the Material Master.
C)  Overall Profile to the Plant dependent Production Order type in the Configuration.
D)  Overall Profile to the Plant independent Production Order type in the Configuration.
E)  Overall Profile to the Production Scheduler in the Configuration.
.

Monday, February 2, 2015

Question no 2585 : Objects for ECN

In SAP Engineering Change Management as at ECC6.0 EhP6, which of the following objects can be subjected to ECN ?

(more than one answers)

A)   BOM.
B)   Routing.
C)   Configuration Profile.
D)   Object Dependency.
E)   Class Characteristics.
.

Sunday, October 17, 2010

Question no : 580 Engineering Change Object Types

In SAP LDM Engineering Change Management ECC6.0, which of the following are valid object types to be included in an Engineering Change Process ?

(more then one answers)

(A)   Object Dependency.
(B)   Bill of Material.
(C)   Task List.
(D)   Characteristics.
(E)   Material.
.