Question no 2487 : PP Master Data

In SAP PP ECC6.0 EhP5, which is correct about the BOM and Routing structure ?

(More than one answers)

A)    You can save a BOM without a header material.
B)    You can save a BOM without a Plant,
C)    You can save a Routing wuthout a header material.
D)    You can save a Routing without a Plant.
E)    You can assign one or more materials to a Routing.
.

4 comments:

  1. A, B) You can create a BOM wihout a Plant but it must have a header material. You then can allocate this material BOM to more than one Plants.

    ReplyDelete
  2. C, D) It is possible to create a Routing without a material but it must be Plant specific, you can then assign one or more materials to this Routing.

    ReplyDelete
  3. E) For a BOM it must be material specific. However, a Routing must be Plant specific and such a Routing can be assigned to multiple materials.