In SAP MM, which of the following is defaulted from the MRP data view when creating the Purchase Info Record for the Material ?
(only one answer)
A) Minimum Quantity.
B) Maximum Quantity.
C) Maximum Stock Level.
D) Planned Delivery Time.
E) Standard Quantity.
.
(only one answer)
A) Minimum Quantity.
B) Maximum Quantity.
C) Maximum Stock Level.
D) Planned Delivery Time.
E) Standard Quantity.
.
Answer: D
ReplyDeleteOnly the Planned Delivery Time from the MRP 2 data view is defaulted to the Purchasing Info Record.