Question no 2538 : MTO Sales Order AV Check

In SAP PP, review the following settings in Strategy 50's Customer Requirement type :


What is the setting affecting Sales Order AV check ?

(only one answer)

A)    No Availability Check is performed, Sales Order item Saved without any ATP Check.
B)    It will perform normal ATP check for Sales Order item as that indicator is only for PP Customer Requirement and not SD Sales Order items.
C)   It is a wrong setting and will result in ATP error.
D)   This indicator is not used for SD, refer to SD config for the correct ATP settings.
E)    When the AV check in the requirement class is switched off like this, the system will perform Availability check using the Planned Independent Requirements.
.

2 comments:

  1. This method of availability check is to 'Check against planned independent requirements':
    . Used with, for example, strategy 50, 60, 52, 63, 74. (All other strategies use ATP check.)
    . Only planned independent requirements are taken into account
    . No MRP elements (for example, stock) are taken into account
    . No requirement to customize the checking rule
    . The field Availability check is only used to determine the requirements passing (daily or individual requirements)