This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, April 29, 2016

Question no 3128 : Plant Parameter and MRP Group Parameter

In SAP MRP as at ECC6.0 EhP6, which of the following MRP parameters can be found in both Plant Parameters and MRP Group Parameters ?

(more than one answers) 

A)   Number Ranges.
B)   Planning Horizon.
C)   Order Types for Planned Orders to Production/Process Orders.
D)   Tolerance for Rescheduling Proposals. 
E)   Planning Time Fence.

Wednesday, April 27, 2016

MM Purchasing - Invoicing Plan (Periodic)

Question no 3127 : Control staggered delivery requirements via MRP mechanics

In SAP MM or PP as at ECC6.0 EhP6, which of the following field in the Lot Size key configuration allows you to set MRP run to generate staggered delivery for a Requirement using Forward or Backward rules ?



(only one answer) 

A)   Lot size indicator and No. of periods
B)   Scheduling method
C)   Date Interpretation
D)   Overlapping
E)   Splitting quota
.

SAP MM : Vendor Evaluation on Goods Receipt Quantity

Monday, April 25, 2016

PM t-code IW12 Document Flow List improvements (ECC6.0 EhP6)

Question no 3126 : PP Strategy

In SAP PP as at ECC6.0 EhP6, which of the following strategy never consider common stocks during the MRP run ?

(more than one answers)

A)  Strategy 10.
B)  Strategy 20.
C)  Strategy 30.
D)  Strategy 40.
E)  Strategy 11.

Friday, April 22, 2016

PP REM : Quota Arrangement Line Load via MRP run into Planning Table of Production Versions

Question no 3125 : Estimated Cost in Maintenance Order

In SAP PM as at ECC6.0 EhP6, which of the following statements are true for Estimated Costs in a Maintenance Order ?

(more than one answers)

A)   Estimated Costs can be entered at Creation Mode only.
B)   Estimated Costs can be entered as long as the Order is not released.
C)   Estimated Costs can be entered as long as the Order is not technically completed.
D)   Estimated Costs can be entered in the Cost Element view and Value Category view.
E)   Estimated Costs can be entered in the Value Category view.
.

PM Capacity Leveling Example

Thursday, April 21, 2016

Question no 3124 : MRP type 'ND'

In SAP PP or MM as at ECC6.0 EhP7, when creating a Material Master for MRP views with MRP type 'ND', which of the following fields are mandatory in the MRP1 and MRP 2 views ?

(only one answer)

A)   Lot size key.
B)   Planned delivery time.
C)   Scheduling Margin Key.
D)   MRP Group,.
E)   Special Procurement key.
.

SAP PM- Preventive simulation on Old Counter on New Sub-Equipment and Offsets

Wednesday, April 20, 2016

Tuesday, April 19, 2016

Question no 3122 : Production Version selection

In SAP PP as at ECC6.0 EhP6, in which of the following you can the settings for selection between automatic Production Version assignment and Manual Production Version assignmenf ?

(Only one answer) 

A)   Material Master MRP4 view.
B)   Material Master Work Scheduling view.
C)   Production Version detail.
D)   Production Scheduler Profile.
E)   Order Type dependent parameter.
.

Existing Counter with new Maintenance Plan (Cycle Start impact)

Monday, April 18, 2016

Question no 3121 : Valuation Class

In SAP MM as at ECC6.0 EhP6, Valuation Class can be directly assigned to which of the following ?

(more then one answers)

A)    MM Account Assignment Category for the Purchasing Documents.
B)    Material Group.
C)    Account Category Reference.
D)    Material Type.
E)    Valuation Type.
.

Sunday, April 17, 2016

Google Sheets : VLOOKUP Basics

Question 3120 : Reset Counter Start-in-Cycle

In SAP Plant Maintenance as at ECC6.0 EhP6, assume the following scenario and select the correct answer ?

A Single-Cycle Counter-Based Maintenance Plan with the following:
. Single-Cycle is 15000 hours
. Current counter reading at 30200 hours,
. Annual Estimate for the Counter is 30000 hours,
At the point of executing IP10, the current latest counter reading was at 30200 hours, and the Planner accidentally set the Start in Cycle counter to zero when performing an On-Line Scheduling.
(All due maintenance orders were already completed at the point of the scheduling and no other maintenance orders were released while future plans are at status 'On Hold')

(only one answer)

A)   No changes to existing plans.
B)   System would issue error message as the current counter is at 30200 hours where No Counter Re-set was found for the counter.
C)   2 Maintenance Orders are created.
D)   1 Maintenance Order is created.
E)    2 new 'On-Hold' scheduled lines are created.
.  

Saturday, April 16, 2016

Question no 3119 : Determining next due for Single-Cycle Counter Maintenance Plan

In SAP Plant Maintenance as at ECC6.0 EhP6, assume the following scenario and deduce the next due date for the Single-Cycle Counter Maintenance Plan

Measuring Point Annual Estimate 30000 km
Single-Cycle Plan at 15000 km
Current Counter reading at 5000 km

Todays data is 15.04.2016, what is the next due date as the Maintenance Plan is scheduled ?

(only one answer)

A)  15.06.2016
B)  15.07.2016
C)  15.08.2016
D)  15.09.2016
E)  15.10.2016
.

Thursday, April 14, 2016

Question no 3118 : Document Flow in Maintenance Order

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following is the only document found in the Document Flow within a Maintenance Order ?

(Only one answers)

A)  Invoice for Stock items.
B)  Payments for Non-Stock Purchase Orders.
C)  Contract for Service Entry Sheet for External Services.
D)  Reservations for Stock items.
E)  Request for Quotation for External Operations.
.

Question no 3117 : Reference Object in Maintenance Plan

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following Reference Objects selections are provided by SAP for assignment to the Maintenance Plan Category ?

(more than one answers)

A)   Functional Location + Equipment + Assembly.
B)   Equipment + Assembly.
C)   Equipment only.
D)   Functional Location only.
E)   Assembly only.

LE Transportation - Assign and Transfer Costs


In this scenario, when perform 'Cost Transfer' of Shipment Cost document in VI02, here the Purchasing Document (long term PO) must be created first as the system will look for the existing PO when trying to generate the service entry sheet into it. (Here, you can use any Purchasing Document Type as it is not the matching criteria when the system search for the PO. Note: IMG - LES - Transportation - Shipment Cost - Settlement - Assign Purchasing Data). 

The matching criteria for PO search is 'Vendor/Forwarding Agent' + Purchasing Organization + Purchasing Group + Plant -> Transportation Planning Plant + Shipment Cost Type.

(You can find in the presentation also some notes on reasons of why the PO was not found/assigned when perform the Cost Transfer)

Alternatively, use SMOD to locate package VTRA for the following user exit
V54U0006 (Shipment PO - Header data supply)
V54U0007 (Shipment PO - Item data supply) 
for enhancement.

(the features are valid as at ECC6.0 EhP6)