This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Showing posts with label Test : Production PPPI - Master Data. Show all posts
Showing posts with label Test : Production PPPI - Master Data. Show all posts

Sunday, May 1, 2016

Question no 3142 : Production version in PPDI and PPPI

In SAP PPPI and PPDI as at ECC6.0 EhP6, which of the following PP master data can be assigned to the Production Version ?

(more than one answers)

A)    Bill of Material.
B)    Standard Routing.
C)    Rate Routing.
D)    Rough Cut Capacity Profile.
E)    Recipe.
.

Question no 3140 : Engineering Change Application for PPDI and PPPI

In SAP PPDI and PPPI as at ECC6.0 EhP6, Engineering Change Notice can be applied to the following objects EXCEPT ?

(only one answer)

A)   Material Master.
B)   Work Center or Resources.
C)   Bills of Material.
D)   Routing.
E)   Recipe.

Thursday, February 25, 2016

Question no 3096 : By-Product and Co-Product

In SAP PPPI as at ECC6 EhP6, which of the following statements correctly describes the setting up of By-Product and Co-Product ?

(More than one answers)

A)  By-Product material is indicated by the 'By-Product' indicator in MRP2 data view.
B)  Co-Product material is indicated by the 'Co-Product' indicator in MRP2 data view.
C)  By-Product material require 'Joint Production' setting in the material master.
D)  Co-Product material require 'Joint Production' setting in the material master.
E)  Both By-Product and Co-Product require a negative quantity when assigned to the BOM.
.

Saturday, February 20, 2016

Question no 3095 : Co-Product for Process Order

In SAP ERP as at ECC6.0 EhP7, the Pre-requisite for Co-Product activation for Process Orders are which of the following ?

(more than one answers)

A)    Co-Product indicator in the MRP 2 data view.
B)    Co-Product indicator when the Co-Product is assigned to the Phase operation in the Recipe.
C)    Backflushing inidcator when the Co-Product is assigned to the Phase operation in the Recipe.
D)    Joint-Production costing setup for the Co-Products.
E)    Price search strategy and apportionment structure in the Costing Variant for the Co-Product Costing.

Friday, February 19, 2016

Question no 3094 : X-Steps and Process Instruction

In SAP PP-PI as at ECC6.0 EhP6, which of the following setting 'locks-in' whether X-Steps and/or Process Instructions are allowed for the Master Recipe ?

(only one answer)

A)   Routing usage.
B)   Default value profile.
C)   Plant parameter.
D)   Production version.
E)   Production scheduler profile.

Wednesday, February 17, 2016

Question no 3093 : Means of Production in PPPI

In SAP PP-PI, the Means of production involved in a production process that have capacities assigned to them is called a _______________.

(only one answer)

A)   Work Center.
B)   Processing Unit
C)   Resource.
D)   Plant.
E)   Labor.

Tuesday, June 17, 2014

Question no 2400 : Valid MRP types

In SAP PPDI (Production Planning for Discrete Indsutry), which of the following MRP types are not valid for the MPS run ?

(only one answer)

A)    M0.
B)    M1.
C)    M2.
D)    M3.
E)    PD.
.

Sunday, June 15, 2014

Question no 2399 : Backflush

In SAP PP and PM, which of the following methods are used to default the 'Backflushing' indicator of a component/parts assigned to an operation of a Task List ?

(more then one answer)

A)    The Backflushing indicator in the 'Status Long Text' in the BOM item detail.
B)    The BOM usage indicators configuration and default to the Item Status in the 'Status Long Text' in the BOM item detail.
C)    The Material Master MRP2 view Backflushing indicator.
D)    The Work Center Backflushing indicator.
E)     The Routing/Task List Header backflushing control indicator.
.

Friday, October 5, 2012

Question no 1688 : Master Recipe Operations

In SAP PPPI ECC6.0, you can assign which of the following to the operations of the Master Recipe ?

(more then one answers)

A)    Primary Resources.
B)    Secondary Resources.
C)    Material Components.
D)    Inspection Characteristics.
E)    Relationships.
.

Thursday, October 4, 2012

Question no 1687 : Master Recipe contents

In SAP PPPI ECC6.0, which of the following are contents possible within the Master Recipe ?

(more then one answers)

A)    Processing steps.
B)    Resources.
C)    Materials.
D)    Personnel number.
E)    Quality Inspection data.
.