In SAP PP or PPPI, the Reduction Strategy in the Routing operations to reduce operation times at MRP run can reduce the following time elements EXCEPT ?
(more than one answers)
A) Queue time.
B) Wait time.
C) Move time.
D) Float before production.
E) Float after production.
.
(more than one answers)
A) Queue time.
B) Wait time.
C) Move time.
D) Float before production.
E) Float after production.
.
Answer: B, D, E
ReplyDeleteThere are two methods of reduction strategy :
ReplyDelete1) Reducing floats before and after production (this is done via IMG for scheduling parameters for planned orders for the plant, order type, and if necessary production scheduler).