SAP QM, the customer would like the be able to change the inspection requirements to less stringent inspection after 10 consecutive accepted inspection lot, and after another consecutive 50 accepted inspection lot; there should be one inspection lot to check the material again .... , which of the following QM feature would you think best suited to address this requirement ?
(only one answer)
A) Sampling Scheme.
B) Supplier Relationship Status.
C) Inspection Point in the Inspaection Plan header.
D) Quality Info Record.
E) Dynamic Modification Rule.
.
(only one answer)
A) Sampling Scheme.
B) Supplier Relationship Status.
C) Inspection Point in the Inspaection Plan header.
D) Quality Info Record.
E) Dynamic Modification Rule.
.
DMR or Dynamic Modification Rule contains the definition for inspection stage changes, the detials which is tracked in the Quality Level for each inspection results.