In SAP MRP, which of the following Parameters only available at the Plant Parameter but not in the MRP Group Parameter ?
(more than one answers)
A) Number Ranges of MRP Elements to created in the MRP run.
B) Planning Horizon.
C) Creation Indicator.
D) Start date in the Past.
E) Purchasing Processing Time.
.
(more than one answers)
A) Number Ranges of MRP Elements to created in the MRP run.
B) Planning Horizon.
C) Creation Indicator.
D) Start date in the Past.
E) Purchasing Processing Time.
.
Review sertings in OPPQ (Plant Parameter) and OPPR (MRP Group Parameter)
ReplyDeleteB) Planning Horizon is avalable in both OPPQ and OPPR , the MRP Group setting ia of a higher priority.
ReplyDeleteC) The Creation Indicator parameter is only available in OPPR MRP Group Parameter.
ReplyDelete