This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, July 25, 2014

Question no 2503 : LTP scneario or LTP planning capabilities

In SAP PP LTP, which of the following the LTP scenario or LTP planning cannot do  ?

(only one answer)

A)    Temporary use a designated MRP type for each material subjected to the LTP scenario planning run.
B)    Switch the Lot-Sizing Rule to a desired one for the LTP scenario planning run.
C)    Ignore the Direct Procurement special procurement key settings for the LTP scenario planning run.
D)    Switch off the time-fence registered in the MRP 1 view for the LTP scenario planning run.
E)    Use the safety stock in the MRP 2 view as the initial stocks for the LTP scenario planning run.
.

4 comments:

  1. A) You cannot switch to a different MRP type for the materials subjected to a particular LTP scenario. However, for Consumption Based Planning material, you can have the LTP scenario planning run to calculate Dependent Requirements for it.

    ReplyDelete
  2. B) There is a Lot Size key you can enter in the LTP planning scenario. This allows you to plan quantities in Periodic Lot Sizing so that the required quantities are consolidated for decision making purpose ie: supplier negotiations.

    ReplyDelete
  3. C) There are many things MTO can be switched off, one of the purpose is to switch off direct procurement as the purpose is not execution but planning only; so the direct procurement process flow is not needed in LTP.

    ReplyDelete
  4. D) You can switch off time fence selectively for each LTP planning scenario.

    ReplyDelete

Note: Only a member of this blog may post a comment.