In SAP MRP, assess which of the following statements are NOT TRUE ?
(more than one answers)
A) A material created using material type 'UNBW' is not for MRP run.
B) A material master with a valid MRP Type must also have an Accounting View.
C) A material with MRP Type 'VB' cannot be assign as a BOM Component.
D) A material with a valid MRP Type but not created with a Purchasing data view will be ignored by the MRP run.
E) A material not assigned to a BOM cannot be subjected to MRP run despite having a valid MRP Type.
.
(more than one answers)
A) A material created using material type 'UNBW' is not for MRP run.
B) A material master with a valid MRP Type must also have an Accounting View.
C) A material with MRP Type 'VB' cannot be assign as a BOM Component.
D) A material with a valid MRP Type but not created with a Purchasing data view will be ignored by the MRP run.
E) A material not assigned to a BOM cannot be subjected to MRP run despite having a valid MRP Type.
.
Answer: A, B, C, D, E
ReplyDeleteA,B) Material with material type 'UNBW' need not have an Accounting view but it is managed with Qty after goods receipt (it is without value), MRP run is possible for this material to plan for its supply.
ReplyDeleteC, E) Material for consumption based planning such as 'VB' for ROP Planning can be subjected to MRP run and it is not dependent on whether it is assign to the BOM or not.
ReplyDeleteD) Both a Finished Goods and a Sub-Aseembly need not have a Purchasing data view but they should have Work Scheduling data view as what is expected of MRP run is to create planned production order.
ReplyDelete