This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, February 28, 2018

Question no 3517 : One Time Vendor in Purchasing Document

In SAP MM as at ECC6.0 EhP6, which of the following Purchasing Documents allows entry of One Time Vendor ?

(more than one answers)

A)  Purchase Requisition.
B)  Purchase Order.
C)  RFQ.
D)  Contract.
E)  Scheduling Agreement.
.

Answer: A, B, C, D, E

PR entry of OTV do not need vendor address. The rest would require vendor address as RFQ, PO, Contract, SAs are all External document and PR is Internal document.

Friday, February 23, 2018

SAP Technical - Change Standard SAP Field Name

Question no 3516 : MASS

In SAP MM as at ECC6.0 EhP6, the "MASS" transaction allows you to perform mass maintenance for which of the following objects in MM ?

(more than one answers)

A)  Material Master.
B)  Purchase Order.
C)  Scheduling Agreement.
D)  Vendor.
E)  Contract.

Goto MASS t-code, F4 on the Object Type Field.

Question no 3515 : Purchasing Requisition Item

In SAP MM as at ECC6.0 EhP6, the Doc Type "NB" for Purchasing Requisition in Standard SAP when creating Stock Scenario expects which of the following field entries ?

(more then one answers)

A)  Item Category.
B)  Account Assignment.
C)  Material Master.
D)  Plant.
E)  Purchasing Organization.
.

Answer: C, D

Item Category Blank or "L" are possible (stock and subcontracting)
Account Assignment is only for Consumable and Services Scenario
Material Master is expected of for Stock Scenario
Plant is necessary for this Logistics Document (most Logistics Documents require Plant)
Pur.Org can be BLANK in PR (Mandatory in PO)

Question no 3514 : PM02 Control Key in PM Order

In SAP PM as at ECC6.0 EhP6, which of the following are required entries for the PM02 Control Key in the Maintenance Order ?

(more than one answers)

A)  Operation Short Text.
B)  Cost Element.
C)  Price.
D)  Vendor.
E)  Requisitioner.
.

Answer: A, B

The following are mandatory:

  • Operation Short Text
  • Cost Element
  • Material Group
  • Operation Qty and UOM
  • Purchasing Group

Purchasing Organization can be BLANK, it not necessary for this scenario.

Monday, February 19, 2018

Plant Maintenance - Do not Change SAP Standard Settings (Item Category in PM)

Question no 3513 : Item Category in Orders

In SAP PM as t ECC6.0 EhP6, which of the following features are delivered by the Item Category in the Maintenance Order ?

(more than one answers)

A)  Creation of Purchasing Requisition from the Order.
B)  Creation of Purchase Order from the Order.
C)  Creation of RFQ from the Order.
D)  Creation of Reservation from the Order.
E)  Initiating MRP run when the Order is Saved.
.

Answer: A, D

OICK

Sunday, February 18, 2018

Question no 3512 : Permit Master Org Structure

In SAP PM as at ECC6.0 EhP6, the Permit Master is created with which of the following Organizational Structure Element ?

(only one answer)

A)  Planning Plant.
B)  Planning Plant + User.
C)  Planning Plant + Equipment/FL Category.
D)  Maintenance Plant.
E)  None.
.

Answer: E

No Org Structure is required, only Permit Category

Wednesday, February 14, 2018

Question no 3511 : Long Term Planning Information System

In SAP PP as at ECC6.0 EhP6, which of the following are Information Systems available for Long Term Planning Scenario Simulation Run Results Analysis ?

(more than one answers)

A)  Material Master Information System.
B)  Purchasing Information System.
C)  Inventory Controlling Information System.
D)  Invoice Information System.
E)  Costing Information System.
.

Answer: B, C

Logistics - Production - LongTerm Planning - Evaluations - Purchasing Information System
Logistics - Production - LongTerm Planning - Evaluations - Inventory Controlling Information System

Tuesday, February 13, 2018

Question no 3510 : Changing Valuation Type of an Equipment

In SAP PM as at ECC6.0 EhP6, in which of the following System Status you can change the Valuation Type in the Serial TAB in the Equipment Master ?

(more than one answers)

A)   AVLB.
B)   INST.
C)   ESTO.
D)   All of the Above.
E)   Not possible.
.

Answer: A, B

Change in AVLB no messages, Change in INST warning message, Change in ESTO error message

Friday, February 9, 2018

Material Management (Pricing) - Condition Index to Change Conditions

Question no 3509 : Material Where-Used List

In SAP PM as at ECC6.0 EhP7, which of the following quantity statistics can be found in IW13 Material Where-Used List Report ?

(more than one answers)

A)  Reserved quantity.
B)  Withdrawn quantity.
C)  Withdrawn with reference to Reservation qty.
D)  Withdrawn without reference to Reservation qty.
E)  Values of the Withdrawn quantities.
.

Answer: A, B, C, D

No values, only quantities

Thursday, February 8, 2018

Question no 3508 : IH01

In SAP PM as at ECC6.0 EhP6, which of the following are possible object display selection in the initial screen of IH01 ?

(more than one answers)

A)   Functional Location.
B)   Equipment.
C)   Equipment Hierarchy.
D)   BOM.
E)   Permits.
.

Answer: A, B, C, D , E

FL, FL Hierarchy, EQ Installed, EQ Hierarchy, BOM (Expand Construction Type), IBase, Permits, Deleted Objects.

Saturday, February 3, 2018

Production Order - Direct Procurement Scenario

Question no 3507 : CC04

In SAP PM as at ECC6.0 EhP6, which of the following are possible functionalities in CC04 Product Structure Browser ?
(more than one answers) 

A)  Create Notification.
B)  Installation of a Functional Location.
C)  Create Orders.
D)  Installation of an Equipment.
E)  Create a BOM.
.

Answer: B, D
CC01 cannot be used for generation of Notification and Order as it is only for master data objects.

Question no 3506 : IH01

In SAP PM as at ECC6.0 EhP6, which of the following are possible functionalities in IH01 FL Structure ?
(more than one answers) 

A)  Create Notification.
B)  Installation of a Functional Location.
C)  Create Orders.
D)  Installation of an Equipment.
E)  Create a BOM.
.

Answer: A, B, C, D 
Try IH01, you can double-click an FL or EQ object to branch to the FL or EQ to perform installations. Within IH01, use menu Goto - Create Notification or Goto - Create Order.

Friday, February 2, 2018

Question no 3505 : IH01

In SAP PM as at ECC6.0 EhP6, which of the following are possible functionalities in IH01 FL Structure ?
(more than one answers) 

A)  Create New Functional Locations.
B)  Installation of a Functional Location.
C)  Create New Equipments.
D)  Installation of an Equipment.
E)  Create a BOM.
.

Answer: B, D

Try IH01, you can double-click an FL or EQ object to branch to the FL or EQ to perform installations.

CO-PP integration of Additive Costs into Cost Estimate for Finished Goods

Thursday, February 1, 2018

Question no 3504 : CC04

In SAP PM as at ECC6.0 EhP6, which of the following are possible functionalities in CC04 Product Structure Browser ? 

(more than one answers) 

A)  Create New Functional Locations.
B)  Installation of a Functional Location.
C)  Create New Equipments.
D)  Installation of an Equipment.
E)  Create a BOM.
.

Answer: A, B, C, D

Try CC04, Right click an FL to see available features.