This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, December 28, 2018

Question no 3609 : Plant Maintenance BOM relevancy

In SAP PM as at ECC6.0 EhP7, to be able to use the Material BOM in Plant Maintenance, the following must be TRUE of the BOM creation ?

(only one answer)

A)  The BOM must be created with the relevant BOM usage.
B)  The Material Master in the BOM Header must be created with Material Type "IBAU".
C)  The Plant for the BOM must be a Maintenance Plant.
D)  The Status of the BOM must be assigned with Plant Maintenance Relevance.
E)  The Header BOM must be set with a "PM" Assembly Indicator.
.

Answer: A

Standard SAP BOM Usage "4" for PM.

Tuesday, December 25, 2018

Question no 3608 : BOM and Routing

In SAP PP as at ECC6.0 EhP7, which of the following data structure are TRUE about PP Master Data ?

(more than one answers)

A)  A BOM can be assigned to one or more Plants.
B)  A Routing can be assigned to one or more Plants.
C)  A Routing can be assigned to one or more Materials for the same Plant.
D)  A BOM can be created without a Material and later assigned to one or more Materials.
E)   A BOM can be created without a Plant and later assigned to one or more Plants.
.

Answer: A, C, E

A, E) When a BOM is created without a Plant, it saved as a Group BOM, but to use it, you must then later assigned it to one or more Plants.
B) A Routing is created specifically for a Plant.
C) A Routing can be created without a Plant but later assigned to one or more materials.
D) In CS01, minimum data is Material, Usage, and Date.


Friday, December 21, 2018

Common Movement Types for Manufacturing MTS Scenario (with Consignment and Subcontractings)

Question no 3607 : MM Physical Inventory

In SAP MM as at ECC6.0 EhP7, which of the following Physical Inventory can be carried out ?

(more than one answers)

A)  Material created from Material Type with Quantity and with Value update.
B)  Material created from Material Type with Quantity and without Value update.
C)  Material created from Material Type without Quantity but with Value update.
D)  Material created from Material Type without Quantity and without Value update.
E)  All of the above.
.

Answer: A, B

As long as with Quantity update.

Friday, December 14, 2018

Question no 3606 : QM Inspection Plan Structure

In SAP QM as at ECC6.0 EhP6, which of the following are TRUE about QM Inspection Plan ?

(more than one answers)

A)  one or more Materials can be assigned to an Inspection Plan.
B)  Inspection Plan can be assigned to Material + Vendor.
C)  Inspection Plan can be both internal and external number range for Group no.
D)  An Inspection Plan can be assigned to one or more Plants.
E)  An Inspection Plan can be assigned to one or more Equipments.
.

Answer: A, B, C

A, B) An Inspection Plan can be assigned to Material or combined Material and Vendor or combined Material and Customer, and one or more of such can be assigned to an Inspection Plan.
C) OQ62 for number range (both internal and/or external are possible)
D) Each Group+Counter only for one Plant
E) at the version mentioned, not possible to assign Inspection Plan to EQ or FL.

Monday, December 10, 2018

Question no 3605 : Hierarchy Task List Structure

In SAP PM as at ECC6.0 EhP7, the following are correct about Hierarchy Task List Structure EXCEPT one ?

(only one answer)

A)  You can create a General Hierarchy Task List, but not Equipment or Functional Location Hierarchy Task List.
B)  The Equipment Hierarchy Task List can be created and assigned to one or more Equipments.
C)  The Functional Location Hierarchy Task List can be created and assigned to one or more Functional Locations.
D)  The Number Range for EQ and FL Hierarchy Task List can have both internal and external Number Range.
E)   A Strategy cannot be assigned to a Hierarchy Task List.
.

Answer: E

A)  You can create General, EQ, or FL Hierarchy Task List (with A, E, T Task List Type indicator).
B, C) Both EQ and FL Hierarchy Task List (as at the version mentioned) can only be relevant or assigned to one EQ or one FL.
D)  The same number range concept applies to General, EQ, or FL Task List as to the Hierarchy Task List. Which means the EQ and FL and Hierarchy EQ and Hierarchy FL Task List can only have internal number range for the Group number.
E)  The Header of the Hierarchy Task List contain: Group number, Counter, Planning Plant, Usage, Status, Short Text, External Identification, Change Number, and Date. 

Friday, December 7, 2018

Question no 3604 : Hierarchy Task List Structure

In SAP PM as at ECC6.0 EhP6, which of the following about Hierarchy Task List are Correct ?

(more than one answers)

A)  Hierarchy Task List Number Range is different from the General Task List Number Range.
B)  Hierarchy Task List can be assigned to the Maintenance Notification.
C)  Hierarchy Task List can be assigned to the Maintenance Item.
D)  Hierarchy Task List has a header with Usage and Status.
E)  Planning Plant is not necessary for Hierarchy Task List.
.

Answer: B, C, D

A) Number Range is shared
E) Planning Plant is necessary for FL, EQ, General, and Hierarchy Task List.

Monday, December 3, 2018

Question no 3603 : Make-to-Stock Strategy

In SAP PP as at ECC6.0 EhP6, a customers production strategy is to produce based on the Forecast, Stocks is the property of Marketing department and therefore it is of no concern to Planning. The Planner further stated that Sales Orders will only be information and should not be included for Production Plan calculations.

Select an appropriate Strategy.

(only one answer)

A)  Strategy 10.
B)  Strategy 11.
C)  Strategy 30.
D)  Strategy 31.
E)  Strategy 40.
.

Answer: B

Strategy 11 "Gross" Planning ignores both stocks and sales orders.