In SAP PP, the following is a Labor Work Center, based on the Work Center data and the Routing presented, what do you think is the Capacity Load if the Production Order is 200 pc ?
(only one answer)
A) 200.0 hours.
B) 180.0 hours.
C) 162.0 hours.
D) 222.2 hours.
E) 246.9 hours.
.
Answer: D
ReplyDeleteRouting is 60 minutes per unit,
ReplyDeletewith Efficiency of 90%, actual production time will be 60 divided by 90% 66.6667 minutes per unit.
total output required 200, therefore total time is 200 x 66.6667 minutes = 13333.3333 minutes
13333.3333 minutes / 60 = 222.22 hours