SAP PP Available Capacity Calculation

In SAP PP, the following is a Labor Work Center, based on the Work Center data and the Routing presented, what do you think is the Capacity Load if the Production Order is 200 pc ?






(only one answer)

A)    200.0 hours.
B)    180.0 hours.
C)    162.0 hours.
D)    222.2 hours.
E)    246.9 hours.
.

2 comments:

  1. Routing is 60 minutes per unit,
    with Efficiency of 90%, actual production time will be 60 divided by 90% 66.6667 minutes per unit.
    total output required 200, therefore total time is 200 x 66.6667 minutes = 13333.3333 minutes
    13333.3333 minutes / 60 = 222.22 hours