Question no : 21 MM Purcasing Auto PO

The "Auto PO" indicator is set in which two master data views below ?

A)   Vendor master Company view & Material master MRP view.
B)   Vendor master Purchasing Org. view & Material master MRP view.
C)   Vendor master Purchasing Org. view & Material master Purchasing view.
D)   Vendor master General data view & Material master Purchasing view.
E)    Vendor master Purchasing Org. view & Material master Basic view.
.

Saturday, December 26, 2009

Question no : 20 MM Purchasing Source Determination

When the system performing automatic source determination for a Purchase Requisition, no source were determined. Deduce why this could happen.

I)    More then one Purchase Info Record from different sources exist.
II)   An in-appropriate lot sizing key was set in the MRP view.
III)  An info record exist for one vendor and A contract exist for another vendor.
IV)  The accounting view of the material master is not yet created.
V)   The Plant was not activated for Automatic Source Determination in the IMG.

A)    I, V
B)    I, III
C)    I, II, III, IV,V
D)    I, IV, V
E)    I, III, V 
.

Question no : 19 QM Quality Level

The Quality department have a requirement to automatically tract the Quality Levels of the incoming raw materials using the SAP QM module, which of the following features you think would most appropriately addressed the requirement before further investigating the matter ?

A)   Sampling Procedure.
B)   Sampling Scheme.
C)   Dynamic Modification Rule.
D)   Quality Info Record.
E)    Inspection Plan.
.