Question no 2822 : Issue Storage Location in Production Version

In SAP PP as at ECC6.0 EhP6, considering that the Production Version was selected, whether this Issue Storage Location in the Assembly is used or the Component Storage Location is used is dependent on which parameter ?


(only one answer)

A)   MRP Group.
B)   Plant Parameter.
C)   Selection Method in the MRP 4 view.
D)   When the Production Version is selected, this Issue Storage Location will always be used.
E)   Production Scheduler Profile.
.

Saturday, October 6, 2012

Question no 1690 : PI Message Monitor

In SAP PPPI ECC6.0, t-code "CO54XT" Message Monitor provides the Controller with which of the following information ?

(more then one answers)

A)    Current processing status of process messages.
B)    Send messages if there are not send by the background job.
C)    Delete messages.
D)    Complete and correct messages.
E)    View messages which are terminated.
.

Question no 1689 : Confirmation of Process Orders

In SAP PPPI ECC6.0, which of the following confirmation options are not possible for Process Orders ?

(only one answer)

A)    Confirmation for Phases.
B)    Confirmation for Secondary Resources.
C)    Confirmation for Operations.
D)    Confirmation for Process Order.
E)    Confirmation via the PI-Sheet.