Question no 2542 : Determine MRP calculation (Min and Max)

In SAP MM or PP MRP, review the following settings and demand situation in the S/R list and determine the SAP MRP calculations. 


(only one answer) 

A)   3 Planned Orders of 500 each. 
B)   1 Planned Order of 1000 and 1 Planned Order of 50. 
C)   2 Planned Orders of 500 each and 1 Planned Order of 50. 
D)   1 Planned Order of 1050. 
E)   1 Planned Order of 1012.
.

1 comment:

  1. Maximum Lot Size of 500 would mean each Planned Order cannot exceed 500.
    Minimum Lot Size of 50 would mean each Planned Order must be at least 50.
    (any lot size in between 50 and 500 is not a problem).
    So, the system would create 2 Planned Orders of 500 each and remaining of 50 on the 3rd Planned Order.