In SAP PP, which of the following Planning Strategy ignores the Planned Independent Requirements in the MRP run ?

(only one answer)

A)    Strategy 10.
B)    Strategy 11.
C)    Strategy 20.
D)    Strategy 40.
E)    Strategy 50.
.

1 comment:

  1. Strategy 20 do not have a Custimer requirement 'Requirement Type' and therefore Planned Independent Requirment entry fro the material is not possible and therefore Demand is driven from Customer Requirement only.