In SAP PP, which of the following Planning Strategy ignores the Planned Independent Requirements in the MRP run ?
(only one answer)
A) Strategy 10.
B) Strategy 11.
C) Strategy 20.
D) Strategy 40.
E) Strategy 50.
.
(only one answer)
A) Strategy 10.
B) Strategy 11.
C) Strategy 20.
D) Strategy 40.
E) Strategy 50.
.
Strategy 20 do not have a Custimer requirement 'Requirement Type' and therefore Planned Independent Requirment entry fro the material is not possible and therefore Demand is driven from Customer Requirement only.
ReplyDelete