In SAP PP for Long Term Planning scenario, evaluate each of the following statements for which ones are CORRECT ?
(more than one answers)
A) You can only assign non-active versions of the PIR to the LTP planning scenario.
B) You can either have active or non-active versions of the PIR but not both in one LTP planning scenario.
C) You can assign PIR versions for only one plant for each LTP planning scenario.
D) You can assign PIR versions of one more more plants for each LTP planning scenario.
E) You can assign PIR with selected periods to each LTP planning scenario.
.
(more than one answers)
A) You can only assign non-active versions of the PIR to the LTP planning scenario.
B) You can either have active or non-active versions of the PIR but not both in one LTP planning scenario.
C) You can assign PIR versions for only one plant for each LTP planning scenario.
D) You can assign PIR versions of one more more plants for each LTP planning scenario.
E) You can assign PIR with selected periods to each LTP planning scenario.
.
Answer: D, E
ReplyDeleteFor each LTP planning scenario, you can :
ReplyDelete. assign one or more plants
. assign one or more versions of the PIR
. assign active or non-active version of the PIR and both possible in one LTP planning scenario
. limit the period to read the PIR planning quantities into the LTP planning scenario or read all data.