Question no 2480 : Maintenance Plan for External Service Procurement

In SAP PM ECC6.0 EhP6, you are not able to assign the following to the Maintenance Plan for external service procurement EXCEPT one ?

(Only one answer)

A)    Cost Center.
B)    More than one Maintenance Item.
C)    Equipment,
D)    General Task List.
E)    Service Master.