In SAP PP MRP run, which of the MRP run options allow review of delay statistics to allow the planner to react to them ?
(only one answer)
A) MD03 Single Item Single Level Planning.
B) MD43 Interactive Planning Single Item Planning.
C) MD02 Single Item Multi Level Planning in Simulation mode.
D) MD01 Total Planning On-Line.
E) MD50 Multi Level Make-to-Order Planning.
.
(only one answer)
A) MD03 Single Item Single Level Planning.
B) MD43 Interactive Planning Single Item Planning.
C) MD02 Single Item Multi Level Planning in Simulation mode.
D) MD01 Total Planning On-Line.
E) MD50 Multi Level Make-to-Order Planning.
.
Answer: C
ReplyDeleteMD43 Interactive Planning mode provides statistics of delay and total delay so as to provide the planner to perform on-line interactive planning to reduce those delays.
ReplyDelete