Question no 3640 : Planning in PP

In SAP PPDI or PPPI as at ECC6.0 EhP6, which of the following is not a Planning Module in PP ?

(only one answer)

A)  SOP.
B)  LTP.
C)  MPS.
D)  MRP.
E)  SFC.

Answer: E

SFC = Shop Floor Control is an Execution Module.

Friday, August 25, 2017

Question no 3430 : PPDI and PPPI

In ECC6.0 EhP6, SAP Manufacturing module in the ERP system, the similarities of PPDI and PPPI are ?

(more than one answers)

A)  Use of SOP.
B)  Use of LTP.
C)  Use of Demand Management.
D)  Use of DRP.
E)  Use of MRP.
.

Answers: A, B, C, D, E

Planning is same for PPDI and PPPI.
Differences are:
1. BOM/Routing for PPDI, Recipe for PPPI.
2. Production Order and Process Order is not exactly the same.
3. Repetitive is only for PPDI while Production Campaign is only for PPPI.
4. PI Sheet is only available for PPPI.

Monday, July 11, 2016

Question no 3209 : Costing with Quantity Structure

In SAP PP or PPPI as at ECC6.0 EhP7, the Costing with Quantity Structure uses which of the following for Planned Cost Calculation ?

(more than one answers)

A)   BOM and Standard Routing.
B)   Recipe.
C)   Based Planning Object.
D)   Inspection Plan
E)   BOM and Rate Routing
.

Sunday, May 1, 2016

Question no 3142 : Production version in PPDI and PPPI

In SAP PPPI and PPDI as at ECC6.0 EhP6, which of the following PP master data can be assigned to the Production Version ?

(more than one answers)

A)    Bill of Material.
B)    Standard Routing.
C)    Rate Routing.
D)    Rough Cut Capacity Profile.
E)    Recipe.
.

Question no 3140 : Engineering Change Application for PPDI and PPPI

In SAP PPDI and PPPI as at ECC6.0 EhP6, Engineering Change Notice can be applied to the following objects EXCEPT ?

(only one answer)

A)   Material Master.
B)   Work Center or Resources.
C)   Bills of Material.
D)   Routing.
E)   Recipe.

Thursday, February 25, 2016

Question no 3096 : By-Product and Co-Product

In SAP PPPI as at ECC6 EhP6, which of the following statements correctly describes the setting up of By-Product and Co-Product ?

(More than one answers)

A)  By-Product material is indicated by the 'By-Product' indicator in MRP2 data view.
B)  Co-Product material is indicated by the 'Co-Product' indicator in MRP2 data view.
C)  By-Product material require 'Joint Production' setting in the material master.
D)  Co-Product material require 'Joint Production' setting in the material master.
E)  Both By-Product and Co-Product require a negative quantity when assigned to the BOM.
.

Saturday, February 20, 2016

Question no 3095 : Co-Product for Process Order

In SAP ERP as at ECC6.0 EhP7, the Pre-requisite for Co-Product activation for Process Orders are which of the following ?

(more than one answers)

A)    Co-Product indicator in the MRP 2 data view.
B)    Co-Product indicator when the Co-Product is assigned to the Phase operation in the Recipe.
C)    Backflushing inidcator when the Co-Product is assigned to the Phase operation in the Recipe.
D)    Joint-Production costing setup for the Co-Products.
E)    Price search strategy and apportionment structure in the Costing Variant for the Co-Product Costing.

Friday, February 19, 2016

Question no 3094 : X-Steps and Process Instruction

In SAP PP-PI as at ECC6.0 EhP6, which of the following setting 'locks-in' whether X-Steps and/or Process Instructions are allowed for the Master Recipe ?

(only one answer)

A)   Routing usage.
B)   Default value profile.
C)   Plant parameter.
D)   Production version.
E)   Production scheduler profile.

Wednesday, February 17, 2016

Question no 3093 : Means of Production in PPPI

In SAP PP-PI, the Means of production involved in a production process that have capacities assigned to them is called a _______________.

(only one answer)

A)   Work Center.
B)   Processing Unit
C)   Resource.
D)   Plant.
E)   Labor.

Thursday, April 23, 2015

Question no 3004 : MRP Area Parameters

In SAP for MRP planning as at ECC6.0 EhP6, which of the following parameters are NOT possible at the MRP area level in the Material Master ?

(more than one answers)

A)   Strategy Group.
B)   Special Procurement type.
C)   Procurement type.
D)   GR processing time.
E)   Planned delivery time.
.

Sunday, March 22, 2015

Question no 2864 : MRP run can delete

In SAP MRP as at ECC6.0 EhP6, SAP MRP run can only delete which of the following ?

(more than one answers)

A)  MRP generated purchase requisitions.
B)  Non-firmed planned orders.
C)  MRP generated production orders.
D)  Manually creates purchase requisition which is not firmed.
E)  Reservations.
.

Question no 2863 : MRP generated planned orders

In SAP MM as at ECC6.0 EhP6, what kind of planned orders characteristics can be generated from an MRP run ?

(more than one answers)

A)   Planned Order with a Supplying Plant.
B)   Planned Order assigned to a Contract.
C)   Planned Order assigned to a Scheduling Agreement.
D)   Planned Order with a Production Version.
E)   Planned Order with a Vendor.
.

Wednesday, March 18, 2015

Question no 2827 : Source List creation

In SAP MM/PP ECC6.0 EhP6, to setup the Source List with the MRP Relevancy Indicator as show, what are per-requisites ?



(more than one answers)

A)   Material Master must have a Purchasing Data view.
B)   Source List requirement indicator is active in the Material Master Purchasing Data view.
C)   Source List requirement indicator is active in the Plant configuration in IMG.
D)   Purchasing Info Record is active for the Material/Vendor combination for the P.Org and Plant.
E)   Purchasing Info Record is active for the Material/Vendor combination for the P.Org without Plant.
.


Question no 2826 : Source Determination during MRP Run

In SAP MM/PP ECC6.0 EhP6, MRP run can perform source determination provided the following is setup ?

(more than one answers)

A)   Contract exist for the Material.
B)   Source List with MRP relevant indicator.
C)   Regular Vendor activation in the customizing.
D)   Source List activate at the Plant parameter.
E)   Purchasing Info Record is active for the material.
.

Question no 2825 : MD01 and MD02

In SAP PP ECC6.0 EhP6, what does MD01 (Toal planning) planning run offers in planning run options that MD02 (Single-item Multi-level) does not offer ?


(more than one answers)

A)  Planning method NEUPL.
B)  Delete-and Recreate MRP data.
C)  User Exit.
D)  Parallel Processing.
E)  Display MRP List,
.

Question no 2823 : Direct Production

In SAP PP as at ECC6.0 EhP6, which of the following statement correctly describe the characteristics of Direct Production ?


(more than one answers)

A) This indicator is set only at the Finished Goods.
B) This indicator is set at the Assemblies.
C) When the planned order for the finished product is converted into a production order, all planned orders for subordinate components that are to be produced directly are automatically converted into production orders.
D) The system displays dependent requirements and planned orders for direct production in a separate direct production segment in the MRP list and the stock/requirements list.
E) Goods Receipt of the assembly directly charged to the superior production order as the assembly is not managed in inventory. 

Question no 2822 : Issue Storage Location in Production Version

In SAP PP as at ECC6.0 EhP6, considering that the Production Version was selected, whether this Issue Storage Location in the Assembly is used or the Component Storage Location is used is dependent on which parameter ?


(only one answer)

A)   MRP Group.
B)   Plant Parameter.
C)   Selection Method in the MRP 4 view.
D)   When the Production Version is selected, this Issue Storage Location will always be used.
E)   Production Scheduler Profile.
.

Tuesday, March 17, 2015

Question no 2815 : Valuation Level

In SAP MM ECC6.0 EhP6, review the following configuration and select the correct answer ?


(more than one answers)

A)  This configuration is define at system installation and cannot be revoked.
B)  The result is the Accounting data view of the Material Master will be at the Company Code level.
C)  Valuation area will be equal to the Plant.
D)  Costing is no longer possible for the installed client.
E)  The result is the Accounting data view of the Material Master will be at the Plant level.
.

Sunday, March 15, 2015

Question no 2801 : S/R List MRP Elements

In SAP MM/PP (ECC6.0 EhP6), which of the following are not MRP Elements presented in the Stocks Requirements List ?

(more than one answers)

A)   RFQ.
B)   Contract.
C)   Inbound Delivery Document.
D)   Inspection Lot.
E)   Delivery Schedule.
.

Saturday, March 14, 2015

Question no 2782 : MRP1, 2

In SAP MRP as at ECC6.0 EhP6, which of the following is not a mandatory field in the MRP view in the Material Master ?

(more than one answers).

A)  MRP Group.
B)  MRP Controller.
C)  MRP Type.
D)  Procurement Type.
E)  Special Procurement Key.
.