Question no 2513 : MRP run

In SAP PP MRP, which of the following statements are TRUE about an MRP run ?

(more than one answers)

A)    In order to perform source determination at MRP run, Quota Arrangement is required.
B)    In order to perform source determination at MRP run, Source List is required.
C)    A material master created with the MRP data view will always be included in an MRP run.
D)    It is possible to delete Planned Independant Requirements that were already in the past via the MRP run.
E)    It is possible to delete Firmed Planned Orders that were already in the past via the MRP run.
.

4 comments:

  1. A, B) Only the Source List is required but the source to be selected must have either ans MRP indicator of '1' or '2' indicator for 'MRP Relevancy' or 'Delivery Schedule creation relevancy' respectively.

    ReplyDelete
  2. C) For a material to be possibly included in an MRP run, it must have a Planning file entry. A Planning file entry is only automatically created for a material if it has a valid MRP type assigned in the MRP 1 data view of the material. (dor example if you assign the MRP type 'ND' for 'No Planning' in the MRP view, the Planning file entry will not be created and hence no MRP run is possible for the Material.

    It is important to also take note that even a Planning file entry can be found for a material, the material will only be included in an MRP run depending on the MRP indicators in the Planning fike entry record.

    ReplyDelete
  3. D, E) Planned Independent Requirementmin the past can only be deleted automatically via Re-Organizatoon transaction codes MD74, MD75, MD76.

    Firmed planned orders in the past can be deleted via an MRP run

    ReplyDelete