In SAP PP or PPPI Planning, identify which planning strategy fits the following scenario ?

"Planned Order with Order type VP is created as supply to Planned Independent Requiremnt, When Sales Order is registered, MRP run will re-create the Planned Order with Order type KD and only at this stage can be converted to Production Order. This strategy is to be set at the Finished Goods."

(only one answer)

A)    Startegy 20.
B)    Strategy 50.
C)    Strategy 60.
D)    Strategy 74.
E)    Strategy 82.
.

4 comments:

  1. A) Strategy 20 is pure MTO where PIR is not allowed.

    ReplyDelete
  2. C) Strategy 60 is for Planning with a Planning material where a Planning BOM is created. Planned Orders from this strategy at the planning material is not convertable to production orders.

    ReplyDelete
  3. D) Startegy is for Assembly Planning and is expected assignment to a Sub- Assembly. Although it js said that this strategy combines the characteristics of Stategy 50 and 70.

    ReplyDelete
  4. E) Startegy 82 is Assembly Planning where at Saving the Sales Order, the Production Order will be created.