Question no 3662 : Estimated Cost

In SAP PM as at ECC6.0 EhP6, Cost Estimate in the Maintenance Order is entered via ?

(only one answer)

A)  Value Category.
B)  Cost Element.
C)  Cost Element Group.
D)  Costing Variant.
E)  Valuation Variant.
.

Answer: A

Wednesday, September 18, 2019

ECC-EWM integration with ECC QM Basic UD only End-to-End Setup and Processing

Question no 3661 : Cumulative Capacity Requirement

In SAP PP as at ECC6.0 EhP6, which of the following allows views of Capacity Requirements for multiple Work Centers ?

(only one answer)

A)  Work Center Hierarchy.
B)  Work Center Grouping.
C)  Work Center Structure.
D)  Work Center Link.
E)  Work Center List.
.

Answer: A

Wednesday, September 11, 2019

Question no 3660 : Goods Receipt Time

In SAP MM as at ECC6.0 EhP6, which of the following is TRUE when Goods Receipt Processing Time is Zero in the Material Master MRP2 data view ?

(only one answer)

A)  Goods Receipt Date = Stock Available Date.
B)  Opening Date = Order Start Date.
C)  Order Start Date = Goods Receipt Date.
D)  Exception Message created at MRP run.
E)  System will use the Plant Parameter Goods Receipt Time.
.

Answer: A


Wednesday, September 4, 2019

Question no 3659 : Purchasing Info Record

In SAP MM as at ECC6.0 EhP6, which of the following are possible for the creation of a Purchasing Info Record ?

(more than one answers)

A)  It can be created without a Plant.
B)  It can be created with a One-Time Vendor.
C)  It can be created without a Material.
D)  It can be created without a Purchasing Organization.
E)  It can be created with a Material Group.
.

Answers: A, C, E

The following are possible:
. Vendor must be permanent vendor and not a One-Time Vendor.
. Plant or without Plant is possible.
. Purchasing Organization is mandatory.
. Material or without Material is possible.
. In-Case without Material then material Group is necessary.