Question no 2544 : MRP Type 'ND'

In SAP MM or PP MRP, when you create a Material with MRP Type 'ND', which of the following data field is mandatory when saving the material with MRP1 and 2 data view ?

(only one answer)

A)   Lot Size key.
B)   Special Procurement key.
C)   Planned delivery time.
D)   In-house production time.
E)   Schedululung Margin key.
.

1 comment:

  1. The Planned Delivery time will still be mandatory, at least you must enter 1 day before the material master can be saved.

    ReplyDelete