In SAP MM or PP, if the Material Master MRP 1 view's MRP type is set with 'ND' for material type 'ROH', which of the following data fields becomes optional ?
(more than one answers)
A) MRP Controller.
B) Lot Size.
C) Scheduling Margin Key.
D) Planning Unit of Measure.
E) Planned Delivery Time.
.
(more than one answers)
A) MRP Controller.
B) Lot Size.
C) Scheduling Margin Key.
D) Planning Unit of Measure.
E) Planned Delivery Time.
.
Answer: A, B, C
ReplyDeleteD) There is no such field called Planning Unit of Measure.
ReplyDeleteE) Since it is external procurement item, the Planned Delivery time in the MRP2 view would still be mandatory as it is not only for MRP run.