Question no 3667 : MRP for PP

In SAP PP as at ECC6.0 EhP6, which of the following is the setting for MRP run when the system first looks for a Routing, if Routing was not found, it will then revert to check either the Lot Size dependent data or Lot Size independent data in the Material Master ?

(only one answer)

A)  Basic date scheduling.
B)  Detail date scheduling.
C)  Routing date scheduling.
D)  3 stage date scheduling.
E)  Lead time scheduling.
.

Answer: E

Lead time scheduling.

Wednesday, October 23, 2019

Question no 3666 : Enterprise Structure in MM

In SAP MM as at ECC6.0 EhP7, which of the following in not assigned to the Enterprise Structure ?

(only one answer)

A)  Plant.
B)  Storage Location.
C)  Purchasing Organization.
D)  Purchasing Group.
E)  Company Code.
.

Click "1 comment" to view suggested answers

Wednesday, October 16, 2019

Question no 3665 : External Services

In SAP MM as at ECC6.0 EhP6, which of the following can use External Services with Service Masters ?

(more than one answers)

A)  Production Order.
B)  Maintenance Order.
C)  Service Order.
D)  Network Order.
E)  Purchase Order.
.

click the "1 comment" to show suggested answers

Wednesday, October 9, 2019

Question no 3664 : Maintenance Notification

In SAP PM as at ECC6.0 EhP6, which of the following is not true about a Maintenance Notification ?

(more than one answers)

A)  It can be assigned to a PM Order to collect costs.
B)  It can be generated via Saving a Maintenance Order.
C)  It can be assigned with one or more General Task List.
D)  It can be created without a reference Object.
E)  It can be closed without converting to a Maintenance Order.
.

Click on "1 comment:" for suggested answer

Wednesday, October 2, 2019

Question no 3663 : Sampling Procedure with different Lot Sizes

In SAP QM as at ECC6.0 EhP6, to achieve sample size for different lot size ranges, which of the following is necessary ?

(only one answer)

A)  Sampling Scheme.
B)  Dynamic Modification.
C)  Inspection Type activated in the IMG.
D)  Inspection Lot Document Type activated in the IMG.
E)  Material Specification.
.

Answer: A