In SAP MM as at ECC6.0 EhP5, when creating a Purchase Order, you can reference to which of the following documents ?
(more than one answers)
A) Material document.
B) Quotation.
C) Contract.
D) Scheduling Agreement.
E) Another Purchase Order.
.
(more than one answers)
A) Material document.
B) Quotation.
C) Contract.
D) Scheduling Agreement.
E) Another Purchase Order.
.
A) As at ECC6.0 EhP5, it is not yet possible to create a PO referencing from line items in the material document.
ReplyDeleteD) Scheduling agreements are released via Delivery Schedules. Therefore, it has no relationship to the Purchase Order.
ReplyDeleteB, C, E) As at ECC6.0 EhP5, you can create Purchase Order with reference to the following:
ReplyDelete. Purchase Requisition
. Contract
. Quotation
. Another Purchase Order