In SAP MRP, which of the following situations will the system update the NETCH flag in the planning file entry for a material ?
(more than one answers)
A) When demand supply imbalance introduced within the planning horizon.
B) When demand supply imbalance introduced outside the planning horizon.
C) When the lot size key in the material master was changed.
D) When the MRP Controller in the material master was changed.
E) When you introduce the MRP Group to the MRP1 view where before it was blank.
.
(more than one answers)
A) When demand supply imbalance introduced within the planning horizon.
B) When demand supply imbalance introduced outside the planning horizon.
C) When the lot size key in the material master was changed.
D) When the MRP Controller in the material master was changed.
E) When you introduce the MRP Group to the MRP1 view where before it was blank.
.
A, B) NETCH is flagged as long as there are changes in demand supply relationships regardless of the planning horizon. (effectively only the NETPL flag is considering planning horizon demand supply relationships).
ReplyDeleteC, D, E) parameter changes in both material master MRP views and the MRP configuration will dictate the settings to NETCH flag to indicate MRP plan inclusion in case the changed parameters affects the new calculations. However, it is logical to understand changing lot size key and mrp group will required NETCH flag as parameters in these 2 fields affect MRP calculation; but in SAP even when MRP controller is changed, it will required NETCH flag as the system needs to update the new MRP controller into the various planned orders created in the previous MRP run.