In SAP MRP ECC6.0 EhP6, Lead Time Scheduling selection for MRP run does which of the following ?
(more than one answers)
A) Calculates both Basic Dates and Schedule Dates for a Planned Order.
B) Calculates only Scheduled Dates for a Planned Order.
C) If Routing is not found, it will look for scheduling data in the Work Scheduling view in the Material Master.
D) If Routing is not found, it abandons the MRP run for the Material and record Exception Message 'No Routing found'.
E) Capacity Plans are calculated.
.
(more than one answers)
A) Calculates both Basic Dates and Schedule Dates for a Planned Order.
B) Calculates only Scheduled Dates for a Planned Order.
C) If Routing is not found, it will look for scheduling data in the Work Scheduling view in the Material Master.
D) If Routing is not found, it abandons the MRP run for the Material and record Exception Message 'No Routing found'.
E) Capacity Plans are calculated.
.
A, B) Both Basic Dates and Scheduled Dates are calculated (standard SAP).
ReplyDeleteC, D) First priority Routing, if not found it looks for scheduling data in the Work Scheduling data view in the Material Master.