In SAP MRP, which of the following parameters is NOT available in the Scheduling Margin Key ?
(only one answer)
A) Opening Period.
B) Safety Time.
C) Float before Production.
D) Float after Production.
E) Release Period for Production Order.
.
(only one answer)
A) Opening Period.
B) Safety Time.
C) Float before Production.
D) Float after Production.
E) Release Period for Production Order.
.
Answer: B
ReplyDeleteSafety Time is set in the MRP 2 data view in the Material Master.
ReplyDelete