Question no 2599 : Firmed Planned Orders

In SAP MRP, select the only FALSE tatement about MRP generated planned orders ?

(only one answer)

A)  Planned Orders can be generated by an MRP run or manually created.
B)  You can convert Planned Orders to Purchase Requisition but not to Purchase Orders.
C)  Firmed Planned Orders cannot be deleted by an MRP run.
D)  Procurement Type in the Material Master will determine if a Planned Order can be converted to Purchase Requisition or Production Order or both.
E)  A vendor can be recorded in a Planned Order through source determination in an MRP run.
.

1 comment:

  1. MRP Group parameter has a tolerance parameter that allows you to delete firmed planned orders.

    ReplyDelete

Note: Only a member of this blog may post a comment.